Ruminant Biotech aims to equip 100 million cows with Emitless methane-reducing tech
New Zealand's Ruminant Biotech says that while it has big goals, the scale of the problem it seeks to solve requires it.
A 50% improvement in resource consent processing times could be necessary for New Zealand to meet its 2050 emissions targets.
That’s according to new research commissioned by Te Waihanga, the New Zealand Infrastructure Commission and developed by Sapere Research Group.
The Infrastructure Consenting for Climate Targets report looks at how much energy and transport infrastructure the country requires to support the transition to a low emissions economy.
Researchers modelled how long it would take to process the necessary consents under the Resource Management Act (RMA) and what it might cost if New Zealand failed to develop the necessary infrastructure.
The report states that total demand on New Zealand’s consenting system from all sectors is projected to increase by over 40% by 2050.
The researchers found that trends in consenting processes indicated that the ability of the consenting system to deliver on the infrastructure required to meet national climate targets is under threat.
“Consenting a project, particularly a complex infrastructure project, is becoming more costly, takes longer to complete and requires more resources,” the report reads.
“New Zealand is on track to miss between 11 – 15% of the emission reductions required from the energy and transport sectors by 2050 due to consenting delays… As a result of consenting delays in these scenarios, New Zealand is on track to incur an emissions liability of between $5 billion and $7 billion by 2050.”
Te Waihanga chief executive Ross Copland says that in an earlier study of consenting costs, Sapere Research Group had identified that since 2014/15 consent times have blown out by 150%.
“Everyone agreed that was a worrying trend but until now we could only speculate on what the implications of longer consenting times would be,” Copland says.
He says the report only reinforces the need to reverse increasing consent processing times if the country wants to meet its Net Zero 2050 commitment.
“Slow or uncertain consenting times heighten the risks face by infrastructure providers through higher project financing costs, delays in awarding contracts or the procurement of critical materials with long lead times,” Copland says.
He adds that those slow or uncertain consenting times can also act as a barrier to new market entrants looking to invest and reduce infrastructure pipeline certainty.
“These issues have significant implications for our environment goals,” he says. “If we can’t reverse this trend of slower and more complex consenting, New Zealand simply won’t be able to build the energy, transport and other infrastructure we need to achieve our 2050 emissions target.”
Hosted by ginger dynamo Te Radar, the Fieldays Innovation Award Winners Event put the spotlight on the agricultural industry's most promising ideas.
According to DairyNZ's latest Econ Tracker update, there has been a rise in the forecast breakeven milk price for the 2025/26 season.
Despite the rain and a liberal coating of mud, engines roared, and the 50th Fieldays Tractor Pull Competition drew crowds of spectators across the four days of the annual event.
Nationwide rural wellbeing programme, Farmstrong recently celebrated its tenth birthday at Fieldays with an event attended by ambassador Sam Whitelock, Farmers Mutual Group (FMG), Farmstrong partners, and government Ministers.
Six industry organisations, including DairyNZ and the Dairy Companies Association (DCANZ) have signed an agreement with the Ministry for Primary Industries (MPI) to prepare the country for a potential foot and mouth outbreak.
The 2026 Red Dairy Cow conference will be hosted by New Zealand in March.
OPINION: ACT MP Mark Cameron isn’t everyone’s cup of tea, but he certainly calls it how he sees it, holding…
OPINION: Did former PM Jacinda Ardern get fawning reviews for her book?